Utrecht’s executive board has approved the preliminary design for redesigning the Lanslaan and part of the Lomanlaan as a cycling and walking street, with more space for cyclists, extra greenery and a new sewer. The street is part of a new, green connection for cyclists and pedestrians between Kanaleneiland, Merwede, Rivierenwijk and the city centre. The route will eventually have room for about 9,000 cyclists per day, and the plans involve a total investment of €4.5 million.

What changes on the streets

The new walking and cycling route runs from the Europalaan to the Beneluxlaan. The Lanslaan and Lomanlaan become cycle streets, which means cars are guests and the carriageway is laid in red asphalt. The carriageway will be 4.80 metres wide in total. Traffic on the Lanslaan gets priority over the side streets.

Parking moves to one side of the street: 20 spaces return on the Lanslaan and 11 on the Lomanlaan. The 20 spaces on the Lanslaan include 1 disabled space linked to a licence plate, 1 general disabled space and 4 spaces for electric cars. A clearly marked school zone will be created around the Rafaëlschool.

Greenery, water and the park

  • 15 extra new trees and about 1,600 m² of extra greenery in the two streets
  • a separated sewer system that captures rainwater better and helps prevent flooding during heavy showers
  • green wadis between parking spaces and homes on the Lomanlaan, where water is collected, plus 6 new trees

A new walking and cycling bridge will lead to Park Transwijk. Through the park, a shared path 6 metres wide will be built, 2 metres wider than today, with 3.6 metres for cyclists and 2.2 metres for pedestrians. A second route via the existing Koeriersterlaan will be set up later; no design has been made for it yet.

Residents’ input

Residents, the Fietsersbond, Woonin, the Rafaëlschool and other stakeholders took part in drawing up the design. Their responses led to more space for pedestrians on parts of the Lanslaan and extra attention to traffic flow and parking. Residents raised concerns about the loss of 33 parking spaces; the city’s study shows there will still be enough spaces. Talks with residents on the concept design ran from 6 July to 2 August 2026, after the starting points and functional design were adopted on 2 December 2025.

What happens next

WhenWhat
End 2026Final design and sewer works design
2026-2027Design of the bridge, final design
2028Sewers and cycle street Lanslaan-Lomanlaan
2028-2029Bridge and path through the park

The city expects works to start in early 2028.